Wednesday, December 14, 2011

Phase 1 Sunrail Concept - Meadow Woods Transit Oriented Development (Orange County, FL) - 50 Year Plan

Plan Radius: 1/2 Mile (10 minute walk) 
Projected Population within 10-Minute Walk: 3200-4000
Current Access: South Orange Avenue (North/South Primary)
Highway Access: 417 (exit located immediately south of Master Plan Area)
Future Access: Direct Sunrail link (2013-2015)

Priority Edits for Phase II Concept (Coming May, 2012)
1) Conserve the wetland to the west of the station area.
2) Review and edit plan area around bald eagle nest to the north of the station area.
3) Gas station (Wetherbee Road) retrofit.
4) Phasing - Long term  (25-50 year) plan includes development along Orange Avenue.
5) Further transformation into a "neighborhood center" as defined by FDOT. 
6) Meadow Woods Golf Course Retrofit - Holes 1-9 (south of Master Plan Area)

Project Team
Tim Maslow - Sustainability factors, concept development, street sections
Mary Moskowitz - Concept development, transportation, street sections
Clark Sprinkel - 3D rendering, concept development
PJ Smith - Master Plan and concept development


Existing Conditions and Plan Radius (1/2 Mile Radius around Station Area)








Green Space Connectivity


No comments:

Post a Comment